Can Your Team Take on a New Project? A Capacity Check for Small Teams
TeamBoard Editorial
Estimate available hours by role before promising a new project deadline.

Before promising a delivery date, calculate how many hours each role can contribute during the project. Subtract existing commitments, meetings, and expected absences, and leave time for changes. A team can have enough hours in total while the person needed for a critical step is fully booked.
Calculate capacity for the delivery window
Break a multiweek project into weeks. The design work may be needed before writing or approval can begin. For each role, subtract current work, meetings, time off, and a buffer from scheduled hours. If the new project estimate already contains a review buffer, count those hours once.
Example: a launch page due next week
Design: 40 working hours minus 24 committed, 5 for meetings or absence, and 3 for changes leaves 8 hours. The project needs 12, a shortfall of 4.
Writing: 40 minus 23, 4, and 3 leaves 10 hours. The project needs 6, leaving 4.
Review: 12 minus 5, 2, and 1 leaves 4 hours. The project needs 3, leaving 1. The team has 22 hours available and needs 21, but it still lacks four hours of design capacity. Writing time only helps if the writer has the skills and availability to take on some design work.
Decide what can change
Agree on a smaller first deliverable, set a later deadline, move an existing commitment with its owner's approval, or assign a specific part of the work to another qualified colleague. Check the sequence again. Extra design hours on Thursday afternoon cannot help a review due Thursday morning.
A checklist before you reply
Write down the requested date and final review time.
List deliverables, dependencies, and approvers.
Compare available and required hours by role and week.
Record each shortfall, the decision, and any impact on other commitments.
Confirm when the client must provide inputs. Keep the calculation in the tool your team uses for planning. In TeamBoard, create a task for each deliverable, assign an owner and due date, and record estimated effort in the description. Update the affected task and revisit capacity if an approval slips. See how small teams organize projects in TeamBoard.